Implementation of a new Distribution Network design with a client
Client Description
Mid-cap manufacturer and distributor of sporting goods to North America and Europe.
Background
The client requested TPG to evaluate and recommend changes to their existing distribution network which resulted in an option to be executed per a defined timeline.
Objectives
Transfer distribution and warehousing responsibilities to a Third Party Logistics (3PL) provider to manage 60% (by volume) of the client’s shipments.
TPG Approach
TPG assumed the role of co-project manager in the implementation of the this project. TPG led monthly reviews of the project and initiated solutions to emerging or present problems. Project sponsors were involved as necessary in these reviews.
Impact/Results
All financial project objectives were either met or exceeded. Final startup of the new facility met or beat the implementation timing objective.